Prefab Ramp Beam – 9 Storey Multi-user Industrial Development at Buroh Crescent

Year: 2014

Project Details:This project required the supply of prefabricated ramp beams measuring 12m x 1m x 0.8m. Each beam, weighing 4.9MT, was installed in 15 minutes by 4 workers, and required another 2 hours to secure anchorage bars at each end. In comparison, it would have taken 4 workers 2 days to tie each beam manually. This thus translated to a time savings of 1.5 days per beam.