Prefab Staircase Wall – 6 Storey Industrial Factory at Senoko

Year: 2015

Project Details:The project scope involved providing reinforcement for a 3m x 5.8m x 6m staircase wall. The wall reinforcement was re-detailed into 6 prefabricated panels to suit manufacturing, transportation and installation requirements.

Each panel was installed in 15 minutes by just 4 workers.Theworkers took a further 2.5 hours to complete the wall by tying the connection bars. This translates to a productivity rate of 1.7 man-hours per MT. Employing conventional methods of installation, these workers would have taken 2 days to complete the job. In this regard, our client achieved a savings of 1.5 work days by leveraging on the use of our prefabricated wall panels.