Ramp Slab – Public Housing Development Multi-Storey Carpark at Clementi Ave 6

Year: 2015

Project Details:Our single directional mesh was re-detailed into a fan shape, so that each piece could be laid according to the curvature of the ramp. 12m longitudinal loose bars were then laid on top of the single directional mesh.

In all, 4 workers took 2 days to complete the ramp slab reinforcement – which translates to a productivity rate of 10.7 man-hours per MT. Conventional methods of tying loose bars would have taken 4 workers at least 4 days to complete, yielding a time savings of 2 days.