Roof Slab Mesh – HDB Multi-Storey Carpark at Keat Hong

Year: 2015

Project Details: BRC was tasked to supply reinforcement mesh for a HDB multi-storey carpark roof slab at Keat Hong. We used our single directional F13100 mesh, instead of the conventional D13 topping mesh.

6 workers deployed for the job laid the single directional mesh in 9 hours, which works out to a relatively high productivity rate of 4.9 man-hours per MT. In contrast, it would have taken 2.5 days to complete the same job using conventional mesh.