The use of prefab panels for the construction of lift walls improved productivity by more than 4 times.
Project Requirements:
Location
8 Yung Ho Rd, Singapore 618590
Using prefab panels, it took just 4 workers 8 hours to complete each of the 9-metre high lift walls, including installation of all the loose links and connection bars.
Technical specifications of lift wall: 1.1m (W) x 1.98m (L) x 9.0m (H); Total weight: 9.4MT
Productivity using non-prefabricated methods: 14 manhour/MT
Productivity using BRC’s prefabrication solutions: 3.4 manhour/MT
4x
Productivity improvement
This was a significant reduction in both the time and manpower that would have been required using non-prefabricated construction methods.