8-Storey Industrial Facility at Jurong West

Project Status: Completed
Project Type: Industrial
Share this project:
The use of prefab panels for the construction of lift walls improved productivity by more than 4 times.
Location
8 Yung Ho Rd, Singapore 618590

Using prefab panels, it took just 4 workers 8 hours to complete each of the 9-metre high lift walls, including installation of all the loose links and connection bars.

所以 11 块钢筋预制板大约 4 小时安装完毕,而安装所有松散的剪力杆和连接钢筋再另用 4 小时。

Technical specifications of lift wall: 1.1m (W) x 1.98m (L) x 9.0m (H); Total weight: 9.4MT

Productivity using non-prefabricated methods: 14 manhour/MT

Productivity using BRC’s prefabrication solutions: 3.4 manhour/MT

4x
Productivity improvement
Reinforcement for the lift walls was delivered as 11 prefab panels.

This was a significant reduction in both the time and manpower that would have been required using non-prefabricated construction methods.