9 Storey Multi-user Industrial Development at Buroh Crescent

Project Status: Completed
Project Type: Industrial
Share this project:
A range of Prefabricated and Cut & Bend solutions helped this industrial development project increase their overall steel fixing productivity.
Location
2 Buroh Crescent, Singapore 627546

For this multi-user industrial development at Buroh Crescent, BRC Asia supported the project with prefab ramp beams, column and post-tensioned slab mesh.

Prefabricated ramp beams could be installed by 4 workers in slightly over 2 hours, as compared to conventional tying which would have taken 2 days.

Technical specifications for Ramp Beam: 0.8m (D) x 1.0m (W) x 12m (L); 4.9MT each

Productivity using non-prefabricated methods: 18 manhour/MT

Productivity using BRC’s prefabrication solutions: 1.8 manhour/MT

10x
Productivity improvement
在 3 名工人的协助下,仅用 4.5 小时就完成了钢筋预制柱的安装。这比需要 5 名工人耗时约 3 天才能完成的传统方法快了 12 倍。

Technical specifications for Column: 3.2m (W) x 1.75m (L) x 9.5m (H); Total weight: 10.8MT

Productivity using non-prefabricated methods: 15.3 manhour/MT

Productivity using BRC’s prefabrication solutions: 1.25 manhour/MT

12x
Productivity improvement
It took 4 workers just 4.5 hours to complete a post-tensioned slab area measuring 600m2 using mesh. This was 5 times faster than manual tying, which would have taken 2 days.

Technical specifications for Post-tensioned Slab Mesh: Slab area measuring 600m2; Total weight: 4.6MT

Productivity using non-prefabricated methods: 21 manhour/MT

Productivity using BRC’s prefabrication solutions: 4 manhour/MT

In each of these tasks involving our prefabricated products, a minimum of 80% of time savings were achieved.

5x
Productivity improvement

Find out how your business can benefit from our tailored reinforcement solutions today.