Reducing both the amount of manpower and time required for reinforcement of shelter walls.
Location
Sengkang, Singapore

It took just 5 hours for 5 workers to install the 23 sheets of mesh/U mesh required for each of the staircase shelter walls at this mixed development project at Sengkang.

通过将楼梯钢筋重新设计为焊网/ U 型焊网,大大减少了安装每面防空壕墙所需的人力和时间。

Technical specifications: Staircase shelter wall of 6m (L) x 3.1m (W); Total weight: 3.5MT

Productivity using non-prefabricated methods: 35 manhour/MT

Productivity using BRC’s prefabrication solutions: 7.2 manhour/MT

5x
Productivity improvement
A fully assembled staircase shelter wall consisting of 23 sheets of mesh.

This was a huge productivity improvement, resulting in time savings of 2 days per floor. Comparatively, the manual process of tying the rebars would have taken 6 workers, 2 days to complete.