Mixed Development at Sengkang
Project Status: Completed
Project Type: Mixed Development
Share this project:
Location
Sengkang, Singapore
Reducing both the amount of manpower and time required for reinforcement of shelter walls.
Project Requirements:
Location
Sengkang, Singapore
It took just 5 hours for 5 workers to install the 23 sheets of mesh/U mesh required for each of the staircase shelter walls at this mixed development project at Sengkang.
Technical specifications: Staircase shelter wall of 6m (L) x 3.1m (W); Total weight: 3.5MT
Productivity using non-prefabricated methods: 35 manhour/MT
Productivity using BRC’s prefabrication solutions: 7.2 manhour/MT
5x
Productivity improvement
This was a huge productivity improvement, resulting in time savings of 2 days per floor. Comparatively, the manual process of tying the rebars would have taken 6 workers, 2 days to complete.
Find out how your business can benefit from our tailored reinforcement solutions.